Large Office Block Refurbishment, Newcastle Upon Tyne. (April 05, 2010)
Total Refurbishment of existing 1960s 2 storey office block within the Newcastle Upon Tyne Area.
 
Cooks Building & Maintenance Ltd is principle contractors on this development.
Contract Value £310,000.00
 
Photograph of Office blocks before works commenced.
 
amec1
 
Rear elevation of premises shown below.
 
amec3841
 
We have cleared away all existing overgrown vegitation from front elevation in preperation for window.
 
amec3976
 
Side Elevation.
 
amec3843
 
The removal of windows have commenced, here you can see the new windows being fitted.
 
amec3960
 
 
amec3962
 
Now security shutters are being fitted to the outside of the new windows.
 
amec3990
 
 
amec3991
 
  amec3992
 
 
amec3995
 
amec4007
 
We have now started to remove the windows from the rear elevation to prepare for new windows.
 
 
amec3998
 
amec07
 
 
amec011
 
amec026
 
amec028
 
amec034
 
amec035
 
All windows and security shutters are completed to rear elevation of premises.
 
amec062
 
amec063
 
amec067
 
All windows and security shutters are now complete to all elevations of building.
 
Works have now commenced with the internal office refurbishments.
 
amec068#
This building has been empty for approximately 15 years
 
wall15
we are now stripping out full building back to brickwork shell
wall17
.
wall18
All existing walls, electrical and heating systems are now being stripped out.
 
wall21
Timber office partitions fitted with Safety laminated glass now devides the offices from the
corridors giving the building a modern look.
 
wall111
All electrical, data and phone lines have now been installed to the full 1st floor office and corridor areas.
 
wall112
.
wall113
.
wall114
.
wall116
.
wall118
.
wall120
Whilst the 1st floor is near completion, you can see the photographs below show works now being completed on the ground floor.
 
 
wall125
The pink walls are fire rated plasterboards which provides the correct level of fire rating for this development.
 
wall129
.
wall131
.
wall132
Works ongoing.
 
Programmed completion date: August
 2010
 
 
This page will be updated soon. 
 
 