![]() Recent Projects. New Driveway (December 07, 2009) New Driveway. This project was to lift existing drive and renew with RMC Beamish Gobble 60mm concrete set. ![]() We have removed all existing drive surface and dug out all soils. We have now excavated down to a good clay base which you can see is approximately 400mm below existing ground level. ![]() ![]() The full area has now been brought back up to correct levels using recycles type 1 and certified crushed hardcore compacted using vibrating roller at regular levels. ![]() Here you can see the border kerbs being laid and concreted in place ready for the laying of blocks. ![]() Its very important to lay a good consolidated base for these types of drives which consist of a min of 225mm compacted hardcore on top of clay. ![]() ![]() ![]() ![]() ![]() ![]() ![]() As you can see, we have now tiled over the step using natural quarry slate which needs to be grouted and sealed. ![]() ![]() All works now completed. More photographs to follow soon!!!!. Click here to return to the Recent Projects page