Extension (July 12, 2007)

This project is to remove existing brick outhouses and build garage, utility and en-suite extension.

alt

We have started to cut outhouses away from main building, prior to full demolition.

alt

16th July 2004.

Site has been levelled and foundations prepared for concreting.

alt

alt

The foundations have not been laid ready to commence building.

alt

alt

A total of 5 Cubmic metres of concrete were used in these foundations. The foundations is 30% larger than specified therefore allowing another extension above at a later date.

alt

Here you can see that the brickwork is now at damp proof course level. (21st July 2004).

alt

Brickwork is now at half way and scaffold has been fitted and loaded with materials.

alt

We expect to be fitting roof within the next few days.

alt

alt

alt

Brickwork is now complete with roof deck fitted.

alt

alt

Here you can see a trench being excavated for new mains water supply, changing from existing lead pipes.

alt

Groundworks along with interior. Estimated completion within 7-10 days.

alt

Remote control electric garage door to be fitted next. alt

alt

This project is now complete. 