This project involves demolition and building works which will allow the land to be sold at a later date.
Site location: Nottingham.
Below is a picture of the existing 300mm thick wall which requires demolition.
Total length of existing wall = 45000mm m by 3200mmm high being 300mm thick consisting of 28,000 hand made bricks.
The work involved is to demolish existing 300mm brick wall, remove concrete infill and make good of brickwork to existing structures.
Below you can see our operatives removing the existing concrete infill and making good of existing walls.
The concrete is now fully removed from the brickwork. We have fully repointed existing brickwork.
The next stage of the project is to fit 2400mm high Heras fencing to the full length and then 1.8m high concrete post and vertilap timber fencing in front.
Here you can see we have fitted a new security steel door leading into the rear of buildings giving caretaker full access to the rear of buildings.
This project is now fully completed.